| 1. | A work structure starts with the highest level, namely the project objective. | 
				
					| 2. | The project objective is broken down into deliverables | 
				
					| 3. | The deliverables are broken down into tasks. | 
				
					|   | NB! The manner in which the tasks are broken down must help to manage the project! | 
				
					| 4. | To make a task more manageable, the smallest task should take no longer than 5 days to complete. | 
				
					| 5. | Each entry is numbered. (In MS Project, you can add a field for "Unique ID", which does automatic numbering.) | 
				
					|   | 
				
					| Example of a work structure | 
				
					| 
 |