1. |
A work structure starts with the highest level, namely the project objective. |
2. |
The project objective is broken down into deliverables |
3. |
The deliverables are broken down into tasks. |
|
NB! The manner in which the tasks are broken down must help to manage the project! |
4. |
To make a task more manageable, the smallest task should take no longer than 5 days to complete. |
5. |
Each entry is numbered. (In MS Project, you can add a field for "Unique ID", which does automatic numbering.) |
|